Building – Contract. The Court of Appeal Civil Division dismissed the appeal by the claimant in a case concerning a building contract held that the contract as amended provided for interim payments to stop at the contractual date for practical completion. There was neither an express term nor any implied term which enabled the claimant to receive interim payments made after the period covered by an agreed schedule governing the making of interim applications and payments.