Building contract – Contractor. The Technology and Construction Court allowed the claimant company's application for declaratory relief in a dispute concerning the payment obligations under a contract and an escrow agreement. The court held that the first defendant had not made a valid interim application within the meaning of the contract, and thus no default event had occurred within the meaning of the escrow agreement.