Building contract – Adjudication. The Technology and Construction Court, on the claimant's application for summary judgment to enforce a decision of an adjudicator, held that, as it had rejected the defendant's challenges to the jurisdiction of the adjudicator and its complaint that the adjudicator had wrongly decided the question of whether the relevant application for payment had been withdrawn, there had to be summary judgment for the claimant as claimed. The present was not one of the rare cases in which there should be a stay of enforcement of any part of the judgment sum.